Berglund Construction was hired to perform the cafeteria renovation at Franic W. Parker School. The project was a total of 2,400 sq. ft. and took 3 months to complete. The scope of work consisted of demolition of existing kitchen and concrete slab, reworking of all mechanical systems for the new kitchen layout as well as new walls, ceilings and flooring. 

The owner refurbished and purchased new kitchen equipment for the installation of the new kitchen. Berglund Construction performed the demolition, concrete, masonry and finish carpentry for the project.

LOCATION Chicago, IL

DURATION 3 Months

SIZE 2,400 Sq. Ft. 

SCOPE Renovation 

DELIVERY METHOD GMP

ARCHITECT Nagle Hartray