This project was a full remodel of an existing ER space. The project was broken down into 4 phases with the completion of phase #1 being 06/2017 and the completion of phase #4 being 10/2018. Phase #1 included updating the radiology space, two radiology rooms and support space. The ER will now include 10 new acute care rooms and two nurse stations for staff support. During phase #1 all the new air handling units, hot water pumps and MEPFP infrastructure were installed.

LOCATION Chicago, IL

DURATION 23 months

SCOPE Renovation

DELIVERY METHOD GMP

ARCHITECT Anderson Mikos Architects