Jewel-Osco
Rain, snow, sleet … in any weather, you can count on Berglund to be there. We slogged through the slush to deliver this Chesterton, Ind., Jewel-Osco store on time, even when winter storms threatened to derail our schedule.
Berglund broke ground on the new store in fall of 2000, and lost four weeks of construction time in December 2000 and January 2001 because of severe weather conditions. Our workers rallied, though, completing the project in six months as originally planned. They did it all without losing any time to accidents, despite the weather. Berglund’s efficient planning, including ordering building materials during the construction phase, helped keep the project on track.
The completed 62,000-square-foot store replaced an existing store of half the size that was located across the street. Berglund constructed the store’s exterior as well as its interior, installing new floors and lighting and replacing the stocked shelves. Our work caught the eye of the Construction Advancement Foundation, which named it the 2001 Project of the Year.